Published: November 27 2023
Excitement fills Hungary as plans for the construction of the southernmost Danube bridge in Budapest are set to commence next year. This new bridge will provide a valuable crossing point on the Danube, improving transportation infrastructure in the region.
Construction Bids and Evaluation Process
The deadline for tender submissions for the Danube bridge and connecting road network in Mohács has passed, and several bids have been received. The evaluation procedure for selecting the contractor is expected to be completed in the spring. The increased number of bids benefits competition, but due to strict rules governing public procurement procedures, further details cannot be disclosed. The decision on the contractor is projected to be made by March 2024, considering the magnitude of the project and the possibility of an extension of the decision period.
Finance and Phases of Construction
The investment for the bridge will be financed through domestic budgetary resources, eliminating dependence on external funding. The tender has been divided into three phases: construction of the connecting road network on the island side, construction of the road network on the urban side, and construction of the bridge itself. Simultaneous construction will begin on each site, with the contractor having fifty months to complete the project from the signing of the contract.
Construction Timeline and Road Development
The 57 motorway section from the M6 motorway to the roundabout in Mohács will be converted into a dual carriageway, with a completion deadline of 21 months. The construction work on the northern edge of the battlefield is slated to finish by 2026, in time for the 500th anniversary of the Battle of Mohács. Additionally, the current 2×1-lane road will transform into a 2×2-lane divided carriageway, with a two-lane turbo roundabout. A 2.7 km dual carriageway will also be constructed from the existing municipal road to the bridge.
Future Plans for the Tisza River
Plans for construction of a new bridge over the Tisza River are scheduled to begin in 2025, further enhancing transportation infrastructure in Hungary.
Exciting developments lie ahead for Hungary as the construction of the Danube bridge and the improvement of road networks bring growth and prosperity to the region.
Questions & Answers
What is the construction project mentioned in the article? The construction project mentioned in the article is the construction of a bridge over the Danube in Budapest.
When is the construction of the Danube bridge scheduled to start? The construction of the Danube bridge is scheduled to start next year.
Where will the Danube bridge be located? The Danube bridge will be located in Mohács, Hungary.
When is the decision on which company will carry out the construction work expected to be made? The decision on which company will carry out the construction work is expected to be made by March 2024.
How long will the contractor have to complete the works? The contractor will have fifty months from the signing of the contract to complete the works.
What are the three phases of the construction project? The three phases of the construction project are the construction of the connecting road network on the island side, the construction of the connecting road network on the urban side, and the construction of the bridge itself.
How long will it take to convert the section of the 57 motorway into a dual carriageway? It will take 21 months to convert the section of the 57 motorway into a dual carriageway.
When is the completion of the construction work on the northern edge of the battlefield expected? The completion of the construction work on the northern edge of the battlefield is expected to be completed by the 500th anniversary of the Battle of Mohács in 2026.
What will be built from the border of Mohács to the bridge? A 2.7 km dual carriageway will be built from the border of Mohács to the bridge.
When is the construction of the new bridge over the Tisza scheduled to start? The construction of the new bridge over the Tisza is scheduled to start in 2025.